Nov 10, 2009
Pictures – paving work progress
We wish to inform you that the work is progressing well. The following are pictures of the paving work done over the last few days. In the next weeks, the contractor will be working on the following:
- The paving of the ramp between E6 and E17
- The concreting of joints between E5 and E6 (above ramp 2) and W1 (west abutment)
- The paving of the E5 and E6 zone (above ramp 2), W1 (west abutment) and the joint with the bridge at E1
- The installation of electric cables for lighting and signalization
- The installation of motorized fences
- The installation of lamp posts and lane signs