Archive for June, 2010

Complete closure of Ramp 4 during the night of June 30 to July 1 – increased traffic between 10 PM and Midnight

We wish to inform the public that Ramp 4 of the Mercier Bridge (on ramp from Chateauguay) will be completely closed to traffic during the night from Wednesday, June 30 at 10 PM until Thursday, July 1 at 5 AM. This closing will permit the installation of streetlights on Ramp 4. Motorists that take this [...]

Work progress as of June 25 – Ramp 3

See the progress of the work to replace the deck as of Friday, June 25 below. We will provide regular updates weekly to illustrate the progress of the work. Click on the picture to enlarge.

Occasional traffic interruptions on the Mercier Bridge detour road

We would like to inform you of the occasional closings for a few minutes on the detour road of the Mercier Bridge between 7 AM and 3 PM on both Wednesday, June 23, and Thursday, June 24, in order to remove concrete slabs from the Ramp 3 deck located above the detour road. These are [...]

A new blog for the Champlain Bridge : www.champlainbridge.ca

We wish to advise motorists of a significant number of night and weekend closures scheduled for the Champlain Bridge and its approaches starting mid June until the end of October. In 2009, the federal government announced that the Champlain Bridge would undergo a ten year major maintenance program of some $212 million starting in 2009. [...]

Work progress as of June 18 – Ramp 3

See the progress of the work to replace the deck as of Friday, June 18 below. We will provide regular updates weekly to illustrate the progress of the work. Click on the picture to enlarge.

Work progress as of June 13 – Ramp 3

We wish to inform you that the work on Ramp 3 of the Mercier Bridge (off ramp toward Châteauguay) is progressing well. See the progress of the work to replace the deck as of Sunday, June 13 below. We will provide regular updates weekly to illustrate the progress of the work. Ramp 4 (on ramp [...]

Detour road: Marking work to take place overnight – June 8

The work on ramp 3 of the Mercier Bridge (off ramp toward Châteauguay) has started well. We invite you to take a look at the pictures taken during the first few days on the worksite, when the first slabs were moved in prevision of their replacement by prefabricated concrete deck panels. Furthermore, following comments received, [...]

Major work by the MTQ in the Saint-Pierre interchange sector (June 4 and 5)

The Ministère des Transports du Québec wishes to inform road users in the metropolitan region that the various projects will result in traffic hindrances this weekend in the Saint-Pierre interchange sector. Hindrances and traffic control Friday June 4, from 11 PM to Saturday June 5, 8 PM Complete closing of the ramp leading to Autoroute [...]

Closing of Ramp 3: Good First Day

It is yesterday that we started an important phase of the rehabilitation project of the Mercier Bridge. As of morning, ramp 3, which is the off ramp toward Châteauguay, was completely closed to traffic for the replacement of its deck. A detour road was suggested to users. This first day at the Mercier Bridge went [...]

Closure of one of two lanes toward the South Shore on the night of June 3 to 4

We wish to inform the public of the closure of one of two lanes on the Honoré Mercier Bridge toward the South Shore, Thursday June 3 from 11 :00 PM to Friday morning June 4, 6 :00 AM. This closure will allow the installation of more signalization panels for the closure of the ramp 3 (toward Châteauguay) [...]