Archive for March, 2011

Honoré-Mercier Bridge: continuation of the inspection work by the MTQ

The ministère des Transports wishes to inform road users that inspection work on the westbound lanes (to Châteauguay) of the Honoré-Mercier Bridge, announced last February, will last for at least one more week. Inspection work respects the following schedule: Friday, 10 PM, to Sunday 21 PM: westbound lanes closure (towards Châteauguay) and counterflow traffic on [...]

Honoré Mercier Bridge – Start of the Second Phase of the Rehabilitation Work on Ramp 2 (La Prairie Ramp) on Monday, March 28 for three months

We wish to inform the public of the start of the second phase of the rehabilitation work on the La Prairie ramp (ramp 2) of the Honoré Mercier Bridge, which will begin on Monday, March 28. Please recall that the first part of the work was carried out last fall and the current roadwork will [...]

Honoré-Mercier Bridge: status of the inspection work – inspection until the end of March

The ministère des Transports wishes to inform road users that inspection work on the westbound lanes (to Châteauguay) of the Honoré- Mercier Bridge, announced past February, will last until the end of March, and respect the following schedule: Saturday, 3 AM, to Sunday 21 PM: westbound lanes closure (towards Châteauguay) and counterflow traffic on the [...]

Notice to LaSalle Residents: Alternating Traffic on LaSalle Blvd. (one direction at a time) CHANGE OF DATES

The following is to inform you that the roadwork, which requires the introduction of alternating traffic on LaSalle Blvd. (and not the complete closure) between Lafleur Ave. and Trésor-Caché Ave., is conditional upon weather conditions (rain). Therefore, the roadwork planned for this week (starting March 17) has been rescheduled.  The obstruction to traffic on LaSalle [...]

Notice to LaSalle Residents: Alternating Traffic on LaSalle Blvd. (one direction at a time) from March 21 to 25 and from March 28 to 30 at the Honoré Mercier Bridge

We wish to inform you of the introduction of alternating traffic on LaSalle Blvd. throughout the course of next week at the Honoré Mercier Bridge. Indeed, from March 21 to 25 and then from March 28 to 30, the installation of temporary traffic lights will allow for alternating traffic on this boulevard, one direction at [...]

REMINDER – inspection work planned by the MTQ to the end of March – counterflow traffic one lane in each direction

The ministère des Transports wishes to remind road users that the inspection work will be performed on the westbound lanes (to Châteauguay) of the Honoré-Mercier Bridge to approximately the end of March as we announced. The results of these inspections will identify and prioritize interventions on the bridge, to eventually allow the return of heavy [...]