Archive for the 'Work progress' Category

Opening of the exit ramp towards Chateauguay (ramp 3) to traffic on September 1st

We wish to announce you the complete opening of the exit ramp towards Chateauguay (ramp 3) to all traffic on the morning of Wednesday, September 1st.
The work that began last June 3rd on ramp 3 was able to be completed in 3 months rather than 4 months, as announced. The contractor, The Mohawk Bridge Consortium [...]

No work this weekend (August 27 to 30) on Mercier Bridge

We would like to advise you that there will not be any work on the Honoré Mercier Bridge this weekend from August 27 to August 30. Considering the major work taking place on the Champlain Bridge, the Mercier Bridge is an excellent option to use.
We wish to remind you important lane closures on [...]

Installation of the anti-jump barriers on Ramp 3

Here are some photos of the installation of the anti-jump barriers that are currently being installed on the Honoré Mercier Bridge.
This barrier borders the future multi-purpose path that will create, upon its completion, a more practical and efficient means between the South Shore and Montreal for both cyclists and pedestrians alike. This path is also [...]

No work this weekend on Mercier Bridge

We would like to advise you that there will not be any work on the Honoré Mercier Bridge this weekend from August 20th to August 23rd. Considering the major work taking place on the Champlain Bridge, the Mercier Bridge is an excellent option to use.
We wish to remind you important lane closures on Champlain Bridge [...]

Work progress as of Sunday August 15 – Ramp 3

See the progress of the work to replace the deck as of Sunday, August 15 below. We will provide regular updates weekly to illustrate the progress of the work.
To see the evolution of our work, please consult our slideshow.

Closures toward the South Shore tonight and tomorrow from 10 PM to 10 AM CANCELLED

We wish to inform the public that the closures planned for tonight August 11 and tomorrow August 12 from 10 PM to 10 AM on the Honoré Mercier Bridge toward the South Shore have been cancelled. The reinforcement work done on the steel structure has been completed more quickly than expected on the upstream part [...]

Work progress as of Sunday August 8 – Ramp 3

See the progress of the work to replace the deck as of Sunday, August 8 below. We will provide regular updates weekly to illustrate the progress of the work.
To see the evolution of our work, please consult our slideshow.

Click on the picture to enlarge.

Work progress as of July 23 – Ramp 3

See the progress of the work to replace the deck as of Friday, July 23 below. We will provide regular updates weekly to illustrate the progress of the work.
To see the evolution of our work, please consult our slideshow below.

Click on the picture to enlarge.

Honoré Mercier Bridge Rehabilitation project – Launch of Phase B

The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) and the Ministère des Transports du Québec (MTQ) are pleased to announce that Pomerleau – Demathieu & Bard S.E.N.C. has been selected as the winning proponent through a public tender in regards to the Honoré Mercier Bridge rehabilitation project – Phase B.
The bridge, opened in 1936 and [...]

Installation of the last concrete deck panels

Here are some photos and video taken in the past few weeks when the last concrete deck panels were installed on Ramp 3, the exit ramp towards Châteauguay. In the next few weeks, post-tensioning and installation work of the new expansion joints will need to be carried out, in addition to the paving that will need [...]